Details for Request 3-195
Request Type: |
Experiment |
Requesting Agency: |
Wisconsin DOT |
State: |
WI |
Date of Request: |
6/27/2006 |
Topic: |
Fishhook Arrow Lane-Use Markings for Roundabouts (also see Official Ruling 2-597) |
Affected Portions of 2009 MUTCD: |
Section 3C.06 |
FHWA Ruling: |
7/11/2006 – Approved request to experiment, with conditions. 11/5/2006 – Approved expansion to additional locations. |
Approval Status: |
Approved |
Keywords: |
Pavement Markings| Roundabouts and Circular Intersections| Symbols |
Contact Information:
|